Site Superintendent
Apr 2021 – Present- Run field operations for tilt-up distribution centers from 400,000 to 1.1M sq ft and $35M to $90M
- Turned over 4 warehouses in 2024–2025, each on or before the contract completion date
- Sequenced 220 tilt panels per building with crane and rigging partners, raising panels in 9 working days
- Lead daily safety walks for crews of up to 180 workers, with zero OSHA citations since 2021
- Run weekly owner and design-team walks, tracking punch items to closeout in Procore